Raise a snag with a photo and a location, assign it, and close it out with a completion photo and a check. Group snags into lists and pin them to the drawing.

Who can do it
Anyone with Create records raises snags, and anyone with Edit records marks them fixed or verifies a fix. Whoever raised a snag is asked to verify it.
Where
Phone (works without signal) and web
Checked
8 October 2026
On this page
  1. 01Raise a snag
  2. 02Pin it to the drawing
  3. 03From open to verified
  4. 04From an inspection
  5. 05Snag list PDF
  6. 06Good to know

A snag (a punch item in the US: same record, your region’s word) is a defect to put right. Snags sit in punch lists, such as “Level 3 finishing defects”, so you can walk, hand over and print them a list at a time.

Raise a snag

On the phone: open the project’s Site tab and choose Snag, or take a photo and choose Create punch item. On the web: open Site → Snags and add one.

  1. The snag. Say what’s wrong, add photos, and choose Where: pick a room or area from the project’s locations, or scan the location’s QR label.
  2. Details. Priority (Low, Medium, High or Critical), who it’s assigned to, and a due date. Assign it to a team member or, with Assign to subcontractor, to a subcontractor from your contacts.
  3. Optionally add it to a punch list. Leave it out and it goes on the project’s default list.

Add another snag starts the next one straight away, for walking a room quickly.

Pin it to the drawing

Open the drawing, choose the Pin tool and tap the spot. Choose Snag as the pin type. The pin shows the snag’s status on the sheet, and opening it opens the snag. When a new revision of the drawing is uploaded, pins can move across to it. See Viewing, marking up and measuring drawings.

From open to verified

Status What it means
Open Raised, not started.
In progress Someone is on it.
Completed Fixed. Completing needs at least one photo of the fixed snag, and an optional note.
Verified Checked and accepted. Whoever raised the snag is asked to verify the fix.
Rejected The check failed. It goes back to the assignee with the reason.

Completed snags wait for a check: they appear under Awaiting you on the phone. Verify or reject a fix on the snag itself, next to the fix photos. Verify All on a list verifies every completed item in one go.

Your own snags are under My snags.

From an inspection

When an inspection has failed items, Create snag from failures turns them into snags, or a whole punch list, in one step. See Inspections.

Snag list PDF

On a punch list, Export PDF makes a snag list with photos, ready to send. On the phone this works without signal for lists already on the phone.

Good to know

  • Without signal, new snags are saved on the phone and sent when signal returns.
  • A snag can also be a warranty item (a defects-period ticket) with a warranty expiry date.
  • Deleting a snag can’t be undone. Most of the time, close it instead.